Thang Long Industrial Park Project- Dong Anh district, Hanoi

Monday, January 29, 2018

Location: Hai Boi commune, Dong Anh district, Hanoi city

Owner: Thang Long Industrial Park Corporation

Period: 2005-2006

 Overview:

Phase 1:

Leveling with 165.000m3 of sand and construction of road arrangement with 8.500m3 quantity

Period: 1998 - 2000
Contract value: 7.573.000.000 VND

Phase 2:

Total area 72ha, Construction of all traffic road system, Transformer station, Power station, Rain water drainage, sewage pumping station, Standing House

Contract value: 29.800.000.000 VND