Package: Construction of the rest of the technical infrastructure items of route N125-N126, line N126-N127, N122A-N170 (section from N101 to N122) – Subdivision A- belonging to Duong Noi New Urban Area Project, Ha Dong District, Hanoi City.
- Construction location: Duong Noi New Urban Area - Ha Dong - Ha noi City
- Investor: Nam Cuong Hanoi Group Joint Stock Company
- Implementation time: September 2020
- Completion time: December 2020
- Project introduction:
In order to implement the general development process of Ha Dong District to 2020 as well as connect with the planning of the Capital region, with the goal of creating a new modern urban axis synchronously in the North of Ha Dong district and connecting with the city. the center of Hanoi capital. Duong Noi new urban area is adjacent to and has an infrastructure system that connects with the infrastructure of Nam Tu Liem district, the area with the fastest urbanization rate of Hanoi capital with many large-scale projects such as the Center National conference, National Sports Center, 5 hotel buildings, Big C supermarket ....
Adjacent to Duong Noi new urban area to the North is a complex of Trade-Tourism-Cultural and new urban areas in the West of Hanoi, which is being planned by Hanoi People's Committee with a scale of nearly 1,000 hectares. Running along the North-West direction is a landscape axis linking functional areas including a 65-hectare square extending the national exhibition center to the northern park of Ha Dong District, along both sides of the square are high-rise buildings. , utilities such as offices, supermarkets, banks ......
To complete the infrastructure system in the urban area, the investor Nam Cuong Group has trusted to choose LICOGI13 Joint Stock Company - Infrastructure Mechanization as the contractor to carry out this bidding package within 3 months with high quality and artistic requirements.
Construction scale:
The bidding package includes completing the rest of the infrastructure, including leveling, construction of storm water drainage, wastewater drainage, road completion, lighting for route N125-N126; routes N126-N127, N122A-N170 – Division A, Duong Noi New Urban Area, Ha Dong District, Hanoi City, including the following jobs:
Structural part of the road surface
- Construction of grade I crushed stone layer 24cm . thick
- Construction of grade II crushed stone layer with thickness of 30cm
- Watering the absorbent layer clinging to the road surface
- Paving the asphalt road surface
Sidewalk part
- Yellow sand 8% cement, thickness 15cm
- Paving, stone floor size 200x200x30mm
- Stone curb, KT 180x150x800cm
- Concrete formwork lining the foundation.
- Concrete lining grade 100.
Rainwater drainage system:
- Digging ditches to lay culverts.
- Transporting land by car.
- Filling ditches and culverts, compacting K95.
- Cushioned crushed stone, 2x4cm stone.
- Supply and install drain base D600.
- Supply and Install drain D600
Sewerage system:
- Digging ditches to lay culverts.
- Transporting land by car.
- Filling ditches and culverts, compacting K95.
- Cushioned crushed stone, 2x4cm stone.
- Supply and install drain base D300.
- Supply and Install drain D300
Lighting system and stone embankment